The incident occurred after a machinery belt broke while a section of the minaret was being removed. The portion subsequently fell onto the mosque’s roof, damaging the structure, said officials.
NEW DELHI — Ujjain’s Shahi Masjid suffered significant damage on Thursday during the demolition of a portion of the structure after a section of its minaret collapsed onto the mosque’s roof, triggering a loud crash and panic among members of the local Muslim community.
The incident came days after members of the Muslim community protested against the demolition order outside the mosque. Tensions had escalated during the protest, with police using lathis and tear gas to disperse demonstrators.
A video recorded on Thursday shows members of the Muslim community standing at a distance as demolition work was underway. A loud crashing sound can be heard as part of the structure gives way, followed by cries of distress from those watching.
According to officials, the incident occurred after a machinery belt broke while a section of the minaret was being removed. The portion subsequently fell onto the mosque’s roof, damaging the structure. No one was injured, officials said.
Ujjain District Collector Roshan Kumar Singh reportedly said the administration was continuously monitoring the situation and that representatives of different communities and local residents were present at the site. He said officials were in regular communication with those present and maintained that the demolition work was being carried out peacefully.
Singh also appealed to people not to pay heed to rumours and said the work was being undertaken with the cooperation of the local community.
He warned that strict legal action would be taken against anyone attempting to disturb the situation by spreading rumours, misleading information or false news through social media or other platforms.
According to Additional Superintendent of Police Guru Prasad Parashar, photography and videography have been prohibited within a 500-metre radius of the site to prevent any disruption to the ongoing work and reduce the risk of injuries.
Ujjain civic body Executive Engineer Rajkumar Rathore said the master plan identifies 2.7 metres of the mosque’s portion from Chhatri Chowk towards Gopal Mandir, along with another 1.4 metres at the opposite end, as falling within the road-widening alignment. A notice had been issued regarding the affected portions, he said.
The road-widening project has also affected shops in the area. Rathore said the demolition work was technically sensitive and was therefore being carried out in phases, with members of the local community involved in the process.